Reorder monthly release tasks for RC1 day
It didn't make sense to merge CE master into EE master, and *then* do the RC1 tasks (e.g., install/update docs) because then the RC1 won't have the updated docs.
This commit is contained in:
@@ -37,9 +37,9 @@ template are explained below:
|
||||
|
||||
### Xth: (6 working days before the 22nd)
|
||||
|
||||
- [ ] Merge CE `master` into EE `master` via merge request (#LINK)
|
||||
- [ ] Determine QA person and notify this person
|
||||
- [ ] Check the tasks in [how to rc1 guide](https://dev.gitlab.org/gitlab/gitlabhq/blob/master/doc/release/howto_rc1.md) and delegate tasks if necessary
|
||||
- [ ] Merge CE `master` into EE `master` via merge request (#LINK)
|
||||
- [ ] Create CE and EE RC1 versions (#LINK)
|
||||
- [ ] Build RC1 packages
|
||||
|
||||
|
||||